Layout Consideration for Heaters, Columns, Tanks
Layout Consideration for Fired Heaters:
- Fired heaters should be located at least 15m away from other equipment that could be a source of liquid spillage or gas leakage.
- To avoid accumulation of flammable liquids, no pits or trenches should be permitted to extend under furnaces or any fired equipment, and if possible, they are to avoided in furnace areas.
- Ensure sample room at the firing front of the fired heater for operation and removal of the burners and for the burners and for the burner control panel, if required.
- Bottom floor fired furnaces require adequate headroom underneath the furnace. Wall fired furnaces require an adequate platforms width with escape routes at each end of the furnace.
- Apart from adequate platform and access to firing front, other structural attachments and platforms around furnace should be kept minimum. Access by means of stepladder is sufficient.
- Arrange fired heaters on a common line, whenever possible.
- Provide unobstructed space for withdrawal.
- Operation and maintenance platforms should be wide enough to permit a 1m clear walkway.
- Escape ladders should be provided on large heaters.
- Vertical heaters usually are supplied with stub supporting feet; ensure drawings show adequate supports elevated to the required height.
- Headroom elevation from the floor level to the underside of heater should be 2.3m to provide good firing control operations.
Layout Consideration for Columns:
- Columns usually are self-supporting with no external structures.
- Circular or segmented platforms with ladders are supported from the shell.
- The maximum allowable straight run of a ladder before a break platform should not exceed 9m.
- The factors influencing column elevation are the provision of a gravity flow system & installation of thermosyphon reboilers.
- Depending on the plant arrangement, columns may have to be elevated to a height in excess of the normal requirements to allow for headroom clearance from lower-level piping off-takes.
- The skirt height of all columns or vessels providing suction to pumps, particularly if handling hot or boiling liquids should be adequate for the pump NPSH requirements.
- Access platforms should be provided on columns for all 3'' and above instrument controller and transmitter, relief valves, manholes and blinds or spades, and other components that require periodic attention.
- Platform for access to level gauges and controllers should not be provided if underside of supporting steelwork is less than normal headroom clearance from grade.
- Adjacent columns should be checked, so that platforms do not overlap. for layout 2.0-2.5 m between shells, depending on insulation, should suffice.
- Allow a 900 mm minimum clearance between column foundation and the adjacent plinth.
- Provide clearance for the removal of internal parts and attachments and for davits at the top of columns, if relevant.
- The center line of manholes should be 900mm above any platform.
- Horizontal vessels should be located at grade, with the longitudinal axis at a right angle to the pipe way, if possible.
- Consider saving plot space by changing vessels from the horizontal to the vertical, if possible and combining vessels together with a internal head (subject to project or process approval).
- The size and number of access platforms on horizontal vessels should be kept to a minimum and are not to be provided on horizontal vessels or drums when the top of the vessel is 2.5m or less from the grade.
- The channel end of vessels provided with internal tubular heaters should face towards an open space. The withdrawal area must be indicated on studies, general arrangement (GAs), and plot plans.
- Internal agitators or mixers are to be provided with adequate clearance for removal. Removal area must be indicated on studies, GAs and plot plans.
Layout Consideration for Tanks:
- The layout of tanks, as distinct from their spacing should always take into consideration the accessibility needed for firefighting and the potential value of a storage tank in providing a buffer area between process plant for example, public roads and houses, for safety and environmental reasons.
- The locations of tank relative to process units must be such as to ensure maximum safety from possible incidents.
Comments
Post a Comment